Projects
Projects
Asset-native delivery: every project linked to assets, finance, and outcomes.
Active Projects
5
In Delivery
4
At Risk
1
Total Budget
$3,869,500,000
Spend to Date
$1,323,800,000
Portfolio Heatmap
Schedule (SPI) × Cost (CPI) performance: circle size = budget
Behind & OverOver BudgetBehind ScheduleOn Track
Smoky Creek & Guthrie Gap Solar + BESS (720MWp / 2,400MWh)
SPI 0.96 · CPI 1.42
Ganymirra & Majors Creek Hybrid Solar + BESS (360MWp / 1,200MWh)
SPI 1.04 · CPI 1.44
Koorangie Energy Storage System (KESS) 185MW / 370MWh System Strength
SPI 1.00 · CPI 1.01
Darlington Point Solar & Riverina BESS Thermal & Inverter Optimisation
SPI 1.35 · CPI 1.55
Lansdown Green Hydrogen Facility Stage 1 (Townsville Eco-Precinct)
SPI 0.83 · CPI 1.86
← Behind scheduleSchedule Performance (SPI)Ahead of schedule →
In Delivery
(4)EDIFY-SCGG-2026
Smoky Creek & Guthrie Gap Solar + BESS (720MWp / 2,400MWh)
Critical
Smoky Creek & Guthrie Gap Solar + BESS
Progress38%
Budget
A$1,850,000,000
-0.4% vs fcst
Target
Mar 2028
In Delivery
EDIFY-GMC-2026
Ganymirra & Majors Creek Hybrid Solar + BESS (360MWp / 1,200MWh)
Critical
Ganymirra & Majors Creek Hybrid Complex
Progress44%
Budget
A$1,350,000,000
+2.1% vs fcst
Target
Feb 2028
In Delivery
EDIFY-KESS-2025
Koorangie Energy Storage System (KESS) 185MW / 370MWh System Strength
High
Koorangie Energy Storage System
Progress94%
Budget
A$410,000,000
-1.0% vs fcst
Target
Dec 2026
In Delivery
EDIFY-DPSF-OPT
Darlington Point Solar & Riverina BESS Thermal & Inverter Optimisation
High
Darlington Point Solar Farm, Riverina & Darlington Point BESS
Progress62%
Budget
A$14,500,000
-2.8% vs fcst
Target
Apr 2027
In Delivery
Complete
(0)No projects